A crew can arrive at the correct gate and time and still lose the morning. Security has an old roster. One required credential review is pending. The foreman planned for cable pulls, but the material has not been released. The paperwork and field plan describe two different starts.
The seven-day check is the last coordination window before dispatch. By then, the contractor should know the first work package, required roles, shift, site conditions, and decision owners. The check does not make an unrealistic start date safe or possible. It exposes what is still open while there is time to correct the plan.
Readiness belongs at the person and workfront level. "Eight of ten confirmed" hides the foreman whose badge is pending. "Materials on site" says nothing about whether the first install package is kitted and released.
Close the gaps while the plan can still move
Start with the work that can actually begin. Name the first assignable task, the drawing or instruction that controls it, and the field leader who can release it. Then build the roster around that work. A broad request for "ten electricians" is too thin if the opening package calls for a working foreman, people with recent conduit-layout experience, and a separate crew for directed material handling.
Changes need a cutoff. If the shift, scope, duration, tools, travel arrangement, or credential requirement moves after the roster is built, the requester should issue a dated revision. Recruiting, security, payroll, and the receiving foreman should work from the same version.
Use a board that shows evidence and authority
Copy this table into the mobilization meeting. "Done" is not evidence. Record a document, approval, field observation, or named confirmation that another person can check.
| Day | Decision to close | Evidence on the board | Decision owner |
|---|---|---|---|
| Seven | Is the crew request current? | Role count, first package, shift, duration, location, tools, and revision time | Project or workforce lead |
| Six | Does each person match the assigned role? | Experience reviewed, required credentials checked, exceptions named | Employer's authorized reviewer |
| Five | Can each person enter the site? | Access package state: not submitted, pending, rejected, or approved | Site access owner |
| Four | Is there released work? | Current drawing, material kit, permits, equipment, predecessor status, and first task | Responsible field lead |
| Three | Have employers coordinated safety? | Hazard, training, PPE, emergency, and reporting handoff recorded | Responsible employer and site safety roles |
| Two | Does each worker have one arrival plan? | Gate, parking, report time, contact, orientation, tools, timekeeping, and acknowledgment | Staffing contact |
| One | Who is cleared for dispatch? | Released roster with role, shift, access state, first task, and receiving foreman | Named go or no-go authority |
The board coordinator keeps the record moving. That job does not grant authority to approve a credential, release a workfront, waive an access rule, or decide that safety training is adequate. Put the actual decision owner in the last column and send exceptions there.
Safety coordination has to happen before arrival
For workers supplied by a staffing agency, OSHA says the staffing agency and host employer share responsibility for a safe work environment. The extent of each employer's responsibility depends on the facts, and OSHA stresses communication about hazards, training, and protections. A staffing checklist cannot transfer those duties to the coordinator or the worker.
OSHA's communication and coordination guidance says contractors, staffing agencies, and their workers should know before arriving what hazards may be present, how exposure will be controlled, and how to report an incident or concern. It also calls for coordination on work planning, scheduling, training, and equipment before work begins.
Use day three to confirm that handoff. Do not label the result a generic safety clearance. The controlling OSHA requirements, employer programs, site plan, task procedures, and decisions by authorized, competent, or qualified people still govern the work.
Review the roster one person at a time
On day one, read the released roster aloud. For each person, confirm role, shift, access state, report instructions, first assignment, and receiving foreman. Give every exception a written disposition: clear it by a named time, replace the person, move the start, change the package, or hold dispatch.
Then walk through the first ninety minutes without inventing perfect timings. Where do workers park? Which gate handles them? Who notices a rejected badge? Where does orientation occur? Who moves the group to the work area? Which field leader can assign the first task? If the gate or orientation room cannot process the whole group together, the site team should set an arrival sequence and communicate it before anyone drives in.
Retire old rosters. The staffing contact communicates the released plan to workers, the access owner updates security, and the field lead confirms the opening package. A reply or acknowledgment is stronger than assuming a sent message was understood.
Dispatch follows the released roster and first package
Before dispatch, ask whether each person can move from arrival to a released task without relying on an unstated assumption. If the answer is no, keep the exception visible and use the named authority path. A delayed or revised start is better than sending someone toward a gate that is not ready to receive them.
If the work package is firm but the electrical roster is still open, send the roles, shift, site, start date, and scope through Rinvio's electrical staffing page. Keep the seven-day board under the contractor's control and update it as the match, access, and field decisions are made.
Sources
- Protecting Temporary Workers, Occupational Safety and Health Administration, accessed July 13, 2026.
- Communication and Coordination for Host Employers, Contractors, and Staffing Agencies, Occupational Safety and Health Administration, accessed July 13, 2026.