When the electrical work on a data center falls behind, the first call is usually for more electricians. Sometimes that is the right call. The 2026 Workforce Survey from AGC and NCCER, which drew 1,830 responses in July and August, found that 42 percent of respondents had projects delayed by shortages of their own workers or their subcontractors' workers. The same survey found 29 percent delayed by long lead times or shortages for electrical equipment, 28 percent by owner orders to halt or redesign, and 26 percent by missing approvals or inspectors.
Only the first of those gets better when you add people.
Name the constraint before you touch the roster
A recovery plan starts with a sort. Take last week's blocked hours and put each one in a bucket: labor capacity, skill mix, supervision, design, material, access, predecessor work, inspection, or an owner decision nobody has made yet. Write the evidence and an owner's name next to each. Most slips have more than one cause.
On data centers right now, equipment is often the bucket that fills first. Medium-voltage switchgear is "often at 40 to 60-plus weeks," says Brennan Church, director of engineering, procurement and construction at data-center developer Hut 8, in Construction Dive. "A shell can be completed and mechanically roughed in, but if the gear isn't onsite, you're not energizing," Church says. "What's driving schedule is equipment lead times," says Lisa Lingerfelt, the DPR leadership team member who oversees megaprojects and strategic accounts, in ENR.
Weather and predecessor trades do the same thing. At the 260-megawatt campus Core Scientific is building for CoreWeave in Denton, Texas, heavy summer rain and wind kept contractors from pouring concrete and cost 60 days, according to TheEnergyMag, which cited The Wall Street Journal. A bigger electrical crew cannot set conduit in a slab that has not been poured. A month before that report, CoreWeave CEO Mike Intrator said in a CNBC interview that when delays turned up at a third-party developer's facility, "CoreWeave responded by deploying our own boots on the ground." He did not name the developer.
Design is the top complaint on the electrical contractors' own list. In the EC&M 2026 Top 50 survey, nearly half of the firms named poor design as the variable with the most effect on finishing on time and on budget, ahead of material delivery (29%) and change orders (15%). Tyler Kautz, regional vice president at PCL Construction, says in ENR that somewhere around 50 to 60 percent into construction the owner's R&D group has to hear "that's enough, no more changes to design." "At some point you have to turn off the innovation spigot," Kautz says.
Overtime tested better than overmanning
When labor really is the constraint, the electrical-only numbers come from an ELECTRI International study by Awad S. Hanna of the University of Wisconsin-Madison, Impact of Overtime on Electrical Labor Productivity (2011), which uses electrical projects from 2004 to 2008. Overtime cut productivity, and the loss grew the longer it ran. Even so, Hanna found that putting an electrical crew on overtime "is more efficient than overmanning." Contractors in the survey liked overmanning least, and the report blames bigger crews, extra tools and congestion.
Of the contractors surveyed, 41.18% named the 5x10 as their typical overtime schedule and 56.86% named it as the one they prefer. Only 31.3% had a company policy on overtime at all.
One of Hanna's cases is an Alabama power plant, where crews hit unexpected red clay and then heavy November rain. Electrical fell behind. The contractor was authorized to work a 5x10, and productivity was tracked for 20 weeks. The loss grew steadily from week 1 to week 11 and was relatively flat after that. On a 36-story Florida condominium, incomplete framing put the electricians on a 6x10, and productivity slid from 100% before overtime to 77% in week 16, then to 55% in the final week.
| Hours per week | Productivity index |
|---|---|
| 40 | 0.97 to 1.02 |
| 50 | 0.88 to 0.92 |
| 60 | 0.78 to 0.83 |
That table comes from a 2005 paper in the Journal of Construction Engineering and Management, reprinted in full in a High Bridge Associates compilation. In its worked example, a project that averaged 61.0 hours a week and used 375,211 work hours during its 67 weeks on overtime lost 22% of its efficiency, or 82,546 work hours. A related Hanna paper on overmanning found losses of 0 to 41 percent, though its data came from 54 mechanical and sheet-metal projects. The pricing arithmetic is in our overtime-versus-flex-crew post.
Electrical work is "last-in-line," Hanna says in the ELECTRI report, and electrical contractors typically end up absorbing delays other trades created. He cites a 1988 finding by Leonard and colleagues that owners refuse time extensions in approximately 73 percent of construction delays. His recommendation is to settle forward pricing for a change request "before expending cost."
Second shifts and long days cost more in injuries
A second shift adds hours without putting more people in the same work area. A 2005 Hanna shift-work paper, also in the High Bridge compilation, concludes that "small amounts of well organized shift work" are an effective response to schedule acceleration. Its model puts the productivity loss between -11% (a gain) and 17% for shift work covering 1% to 50% of budgeted manhours. Those were mechanical and sheet-metal projects.
OSHA's worker fatigue page says accident and injury rates are 18% greater on evening shifts and 30% greater on night shifts than on day shifts. It cites research tying 12-hour days to a 37% increased risk of injury. OSHA's coordination guidance for host employers, contractors and staffing agencies says to "ensure that work is planned and scheduled to minimize impacts on safety," and to have managers with decision-making authority available for day-to-day coordination.
A night shift needs its own foreman.
A new hire takes months to reach full speed
New hires are the slowest fix. Scotty Wristen, owner of WE Electric in Abilene, Texas, now hires teenagers straight out of high school as apprentices. He told The Texas Tribune that new apprentices usually go through four or five months of small mistakes that cost time and money. "It's fixable," he adds. He says he can afford $20 an hour. The data centers pay $35 plus overtime and per diem, and he lost five workers to them. In the same town, Crusoe senior vice president Jamie McGrath told city leaders in March that about 9,000 craft workers are on site every day at the Crusoe and Lancium data center campus, according to KTXS. He expects construction on its eight buildings to last through the first quarter of 2027.
The AGC survey adds that 83 percent of firms report at least some turnover among new field hires in their first 90 days, and that 81 percent of firms with electrician openings have trouble filling them. The shortage runs into supervision, too. Superintendent openings were hard to fill for 75 percent of the firms that had them, and quality-control roles for 66 percent. A compressed job often needs another foreman or QC inspector before it needs ten more hands. Apprentices will not close the gap this quarter. Most electricians learn the trade in a 4- or 5-year apprenticeship, with about 2,000 hours of paid on-the-job training a year, according to the BLS.
A 14-day board shows whether the fix is working
The board borrows make-ready planning from the Lean Construction Institute's Last Planner System, which describes it as "removing constraints ahead of time." For each of the next 14 days, the board shows the work package, the crew by role, the target quantity, the inspection, the constraint owner and the date a decision is due. The daily huddle reviews only the exceptions.
Measure ready backlog, the age of open decisions, material-kit completeness, first-pass inspection results and installed units per shift. A second shift that recovered pathway work may be the wrong tool once the constraint moves to inspections or test documentation, and the board should show that move.
Schedule pressure is not an exception to de-energizing
OSHA's general-industry rule, 29 CFR 1910.333(a)(1), allows work on live parts of 50 volts or more to ground only when the employer can show that de-energizing "introduces additional or increased hazards or is infeasible due to equipment design or operational limitations." A late milestone is neither. On construction sites, 29 CFR 1926.417(b) requires de-energized equipment to be "rendered inoperative" with tags "at all points where such equipment or circuits can be energized." When supplemental electricians join a compressed job, OSHA's temporary worker guidance says host employers and staffing agencies "share responsibility for ensuring worker safety and health."
Write the exit trigger on the first day
Every temporary measure needs an exit trigger written down with it, for example accepted quantities or float back in the schedule. Keep enough electricians for punch and retest. "The resource pool has not grown," says Ben Kaplan, managing director at Turner Construction, in ENR. A crew ready to roll the racks in now may not be free two weeks later, Kaplan says, since "they have to go somewhere else."
Rob Smith, CEO of Sargent Electric in Pittsburgh, says in the EC&M report that his firm's go or no-go call on a job starts with the question "Can we get the people, predict their productivity, and what's the impact of where the job is?" On equipment lead times, Smith says, "we've worked our schedules around it."
Sources
- 2026 Workforce Survey Analysis, Associated General Contractors of America and NCCER, September 3, 2026.
- What's stalling data center projects? Public opposition and power access lead delays., Construction Dive, April 22, 2026.
- Data Center Crunch: Contractors Rethink Project Delivery, Adopt New Tools to Meet Booming Demand, ENR, September 2, 2026.
- Weather Disruptions Delay CoreWeave, Core Scientific AI Data Center in Texas: Report, TheEnergyMag (Wolfie Zhao), December 16, 2025.
- CoreWeave CEO won't say if Core Scientific caused data center delays, both stocks plunge, CNBC (Ashley Capoot), November 11, 2025.
- Data Center Buildout Fuels Revenue Blowout: EC&M's 2026 Top 50 Electrical Contractors Special Report, EC&M, September 15, 2026.
- Impact of Overtime on Electrical Labor Productivity: A Measured Mile Approach, ELECTRI International (Awad S. Hanna, University of Wisconsin-Madison), 2011.
- Impact of Extended Overtime on Construction Labor Productivity, Hanna, Taylor and Sullivan, Journal of Construction Engineering and Management 131(6), June 2005.
- Construction Productivity Impacts due to Extended Work Weeks, Shift Work, & Fatigue, High Bridge Associates compilation (includes Hanna, Chang, Sullivan and Lackney, Shift Work Impact on Construction Labor Productivity, 2005), 2017.
- Impact of Overmanning on Mechanical and Sheet Metal Labor Productivity, Journal of Construction Engineering and Management 133(1), 2007.
- Long Work Hours, Extended or Irregular Shifts, and Worker Fatigue: Hazards, Occupational Safety and Health Administration, accessed September 29, 2026.
- Communication and Coordination for Host Employers, Contractors, and Staffing Agencies, Occupational Safety and Health Administration, accessed September 29, 2026.
- Data centers, Texas home builders compete for electricians, The Texas Tribune, April 28, 2026.
- Report on the Lancium and Crusoe briefing to Abilene city leaders, KTXS (Caitlin Leggett), March 5, 2026.
- Electricians, Occupational Outlook Handbook, U.S. Bureau of Labor Statistics, last modified August 27, 2026.
- Last Planner System, Lean Construction Institute, accessed September 29, 2026.
- 29 CFR 1910.333, Selection and use of work practices, Occupational Safety and Health Administration, accessed September 29, 2026.
- 29 CFR 1926.417, Lockout and tagging of circuits, Occupational Safety and Health Administration, accessed September 29, 2026.